Impact Fee Administrative RegulationsRates Updated for FY10 Sec. 1.0 Definitions:
Sec. 2.0 Effective Date: Impact fees were adopted by unanimous vote of the Burlington City Council on October 13, 1992 and went into effect on November 13, 1992. All covered projects which receive zoning approval on or after this date are subject to impact fees. Sec. 3.0 Covered Projects: Any new development or additions to existing buildings which result in new dwelling units or in new nonresidential buildings square footage are subject to impact fees as is any change of use which results in an added impact according to the Table of Impact Fees in Sec. 5.0. Sec. 4.0 Exemptions: Certain types of development are exempt from impact fees including the following:
Sec. 5.0 Calculation of Impact Fee: Impact fees are based on building square footage as per the following table:
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Sec. 6.0 Distribution of Impact Fees: Impact fees received will be distributed to city departments, upon authorization by the City Treasurer, solely for the purpose of capital projects, according to the Table of Impact Fees in Sec. 5.0 of these regulations. Sec. 7.0 Annual Adjustment: There shall be an automatic annual increase to the impact fee schedule specified in Sec. 5.0 of these regulations as of July 1, 1993 and every July 1 thereafter, equivalent to 100% of the annual change in the Consumer Price Index. Sec. 8.0 Effect of Project Change on Impact Fees: If a proposed development is substantially modified in terms of square footage, a request for an adjustment to the impact fee may be made by filing a zoning permit application subject to the applicable filing fees. Any adjustment, if approved, is subject to the Table of Impact Fees in effect at time of the subsequent approval. Any change which increases a project size or impact shall require a new zoning permit and an accompanying adjustment to the impact fee amount. Sec. 9.0 Demolition or Change to Existing Building: No impact fee rebates shall be authorized for the demolition of an existing building, a reduction in size of an existing building, or a change in the use of an existing building. There are no rebates if one decides to reduce the use of (or is unable to use) one's property for any reason. Sec. 10.0 Time and Place of Payment: Impact fees must be paid to the City's Treasurer's Office according to the following schedule:
Sec. 11.0 School Impact Fee Exemption: That portion of impact fees attributable to school impacts shall not be required for senior citizen housing projects, or for that portion of a project where certain units are reserved specifically for the elderly. Any project, or portion thereof, which meets either state or federal guidelines for elderly housing shall be deemed a senior citizen housing project and eligible for a full or partial waiver of school impact fees. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Sec. 12.0 Affordable Housing Waivers: Any residential project containing newly constructed units or substantially rehabilitated housing units that are affordable for households as described in subsections (a), (b) or (c) are eligible for a waiver of impact fees for that portion of the project. The terms, rules and regulations used herein shall be the same as those defined and specified in the Burlington Zoning Ordinance pertaining to Inclusionary Zoning (Article 9 Part 1).
Sec. 13.0 Median Income Provisions: For purposes of determining median income, the income levels specified in Article 9 Part 1 of the Burlington Comprehensive Development Ordinance, or the most recent amendment thereto, shall be applicable. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Sec. 14.0 Penalties for Nonpayment: If an impact fee is not paid, a certificate of occupancy can be denied, a lien can be placed upon the property, and a fine of $200 a day can be assessed along with other court-imposed penalties. Sec. 15.0 Expenditures of Impact Fees: Impact fees must be used for capital improvements to accommodate the demands created by new growth. The City Treasurer shall maintain records of all impact fee receipts and disbursements by category, and include a summary of same in each City Annual Report. Any expenditure of impact fees must be authorized by the City Treasurer. Sec. 16.0 Time Limit on Expenditures: If an impact fee is not expended on eligible capital improvements by the city within six (6) years of payment, it must be refunded to the property owner by the City Treasurer along with any accrued interest. Sec. 17.0 Relationship to Other Fees: Impact fees do not replace other fees pertaining to development projects. All applicable permit fees, including, but not limited to, development review fees and building permit fees, must be paid prior to occupancy. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
End of Impact Fee Administrative Regulations |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||